Project

Client

Consultant

Date

Rehabilitation Upgrade of Reduction Station valves for unit 1&2KAFR El-DWAAR Power Station

WDEPC

WDEPC

2010

Sandblasting and painting for Gas Pipe Line in KAFER El-DWAAR Power Station

WDEPC

WDEPC

2010

Rehabilitation for Fan Expansion of Gases in Unit 2 Assuit Power Plant

UEEPC

 

2010

Fabrication & Erection of Super Heaters of 150 Ton steam Boiler in Qena Paper Factory

Qena Paper

 

2008-2009

Piping Fabrication & Erection in TRAN 4 in El-Salam Gas Tran.

PETROFAC

 

2008

Fabrication & Erection With Supports of Hot & Cold reheat Pipe Line , Vent Line at Kurimat Combined Cycle Power Plant (750MW)

Skoda Brahe Co.

PEGESCO

2007-2008

Rehabilitation of Boiler No. 2 German Type in South Cairo Power Plant

CEPC

CEPC

2008

Dismantling & Erection of Reheat Pipe Line at Talkha combined  Power Plant

HIDELCO

 

2007-2008

Fabrication of Hot & Cold Super Heaters of 150 Ton steam Boiler in Qena Paper Factory

Skoda Brahe Co.

PEGESCO

2007

Fabrication & Erection for Carbon Steel , Stainless Steel, low Temp.& Doublex Pipe Line in Ras Ghareb

PETROJET

ENPPI

2007-2008

Fabrication & Erection for Carbon Steel , Stainless Steel Pipe Line at Rommana site (El-Arish City)

PETROJET

ENPPI

2007

Installation of Pipe Net of 2 Boiler in Factory of Metallic Oil (Misr-Kanada)

IBSF Boilers & Steel fabrication ”S.A.E”

Misr-Kanada)

2007

Rehabilitation Process of 2 Boilers 68 Ton in Alexandria Petroleum Company

Thyssen Krupp Xervon Energy Germany Co.

APC

2007